CIVIL & INFRA WORKS RIVER & MARINE WORKS

---------------------------------------------- ---------------------------------------------

No

Project Title

Client

Contract Sum (RM)

Completion Date

01

Construction of Telekom Substation at Pulau Jerejak,Penang
(Inc. Cable Lying)

Penang Shipbuilding & Construction Sdn Bhd

270,000.00

September 1996

02

Sabah Gas Metering Skid Project at Sungai Buluh, Selangor

HL Engineering (M)
Sdn Bhd

350,000.00

December 1996

03

Reinforced Concrete Pile caps and Slab Deck Works at JB Water Front

Pilecon GepTechnics Sdn Bhd

570,000.00

April 1997

04

Project Management for Road Works from Jelapang Chemor in
Kinta District Perak

Greenhands Construction Sdn Bhd

150,000.00

August 1997

05

Construction of RC Wall for 2 units of Accomodation Module in Pulau Jerejak,Penang

PSCI Naval Dockyard Sdn Bhd

680,000.00

March 1999

06

Construction and Completion Of Civil/Building Package (Package-1) for Putrajaya District Cooling Plant,Selangor.

Nam Fatt Construction Sdn Bhd

1.1 million

9 Apr 1999

07

Deep Excavation (B09) at Preheater Basin in Manjung Power Plant

Leighton Contractors (M) Sdn Bhd

150,000.00

Jan 2002

08

44 units of Double-storey terraced houses in Mukim Durian Sebatang, Perak

Sunny Triumph Development Sdn Bhd

3.5 million

Sep 2002

09

8 units of Double Storey Terrace Houses for Phase 2A,Taman Cahaya in Teluk Intan ,Perak

Sunny Triumph Development Sdn Bhd

650,000

Dec 2003

10

29 units of Double Storey Terrace Houses for Phase 2B, Taman Cahaya in Teluk Intan ,Perak

Sunny Triumph Development Sdn Bhd

2.32 million

Dec 2004

11

Supply, Install and Construct Paintball Field for "Natural Heritage Orchard & Country Resort" Mukim Kuala Linggi, Daerah Alor Gajah,Melaka Bandaraya Bersejarah

Sri Lingga Sdn Bhd

203,000.00

March 2007

12

119 units mix developments at Taman Panglima in Teluk Intan, Perak

Sunny Triumph Development Sdn Bhd

9.5 million

Sept 2007

13

Earth and Sand works for laluan Dari Pasir Panjang ke Linggi, Negeri Sembilan

Techniques Geosystems Sdn Bhd

11 million

Dec 2007

14

Upgrading of Flood Detention Pond as part of Flood Mitigation Solution for Selangor Irrigation Department and associated structural works in Multimedia Super Corridor(MSC), Selangor, Malaysia

Aliran Musim Sdn Bhd

11.6 million

Feb 2010

15

Proposed Elevated U-Turn on lot PT 292, Bandar Sunway for Taylorís College,Malaysia

3 Face Sdn Bhd

8.4 million

Aug 2010

back to top

RIVER & MARINE WORKS

01

Dredging at the Waterfront of PSC's Yard, Pulau Pinang

Penang Shipbuilding & Construction Sdn Bhd

3.23 million

July 1996

02

Reclamation at Lumut Industrial Port Area (Project in JV with Ballast Nedam Group N.V (M) Sdn Bhd

Lumut Maritime Terminal Sdn Bhd

12.5 million

Nov 1996

03

Reclaimation at Lumut Industrial Area - Phase 2, Perak (Project in JV with Perangsang International Sdn. Bhd.

Lumut Maritime Terminal Sdn Bhd

4.45 million

March 1997

04

Dredging Work in Load-Out Front in Teluk Ramunia,Johor

Promet Fabricators    Sdn Bhd

1.26 million

April 1998

05

Dredging Work in Load-Out Front in Teluk Ramunia,Johor

Sime Sembawang Engineering Sdn Bhd

120,000.00

May 1998

06

Removal of Slope Sand Surcharge at Lekir Coastal Development, Manjung Power Plant,Manjung, Perak

Van Oord ACZ (M)     Sdn Bhd

1.4 million

July 1999

07

Rock Revetment Works at Lekir Coastal Development, Manjung Power Plant,Manjung, Perak

Van Oord ACZ (M)     Sdn Bhd

17.0 million

July 1999

08

Construction Of Outfall Channel Structure in Manjung Power Station,Sitiawan Perak

Leighton Contractors Sdn Bhd

5.4 million

January 2002

09

Rock Reinstatement Works at Lekir at CW Intake in Manjung Power Plant

Leighton Contractors Sdn Bhd

120,000.00

Nov 2001

10

Construction Of Slope Protection System to Ash Pond Bunds

Peremba Construction Sdn Bhd

2.25 million

September 2002

11

Proposed Protection and Beautification of Kota Tinggi River Bank, Sg. Johor, Johor

ACPI Precast Solutions Sdn Bhd

6.5 million

Dec 2003

12

Proposed Replenishment and Beautification of Port Dickson Beach

Apex Beach Management Sdn Bhd

1.8 million

June 2004

13

Supply, Lay and Fix Land and Submarine Pipeline and Associated Works from Lebuhraya Bayan Baru to Pulau Jerejak Pulau Pinang

Perbadanan Bekalan Air Pulau Pinang Sdn Bhd (PBA)

19 million

April 2006

14

Proposed 2 x 700 MW Coal Fired Power Plant Project, Jimah Negeri Sembilan.-subcontract sorks for Shore Protection Works

Taisei Corporation

6 million

Jun 2007

15

Proposed 2 x 700 MW Coal Fired Power Plant at Kuala Lukut,Mukim Jimah ,Port Dickson Negeri Sembilan-Working Platform Preparation for Ground Improvement for Intake Channel

Taisei Corporation

250,000.00

July 2007

16

Dredging work at the waterfront of Oilfab's Yard,Pulau Indah Industrial Park-West Port,Selangor

Intraline Resources Sdn Bhd

2.71 million

Sept 2007

17

Proposed 2 x 700 MW Coal Fired Power Plant at Kuala Lukut,Mukim Jimah ,Port Dickson Negeri Sembilan-Subcontract Works for Construction Completion and Maintenance of the Cooling Water Intake Channel

Taisei Corporation

14 million

May 2007

18

Proposed 2 x 700 MW Coal Fired Power Plant at Kuala Lukut,Mukim Jimah ,Port Dickson Negeri Sembilan-Backfilling Work for Offshore Outfall Culvert

Taisei Corporation

2 million

July 2008

19

Supply & Lay 600MM Steel Submarine pipeline 3.1km from Teluk Batik to Pangkor Island

Lembaga Air Perak

21 million

May 2009

20

Projek Menaiktaraf Sistem Saliran Sg. Rasau Fasa II, - Kolam Takungan Banjir di atas Lot 336 dan kerja-kerja berkaitan -Pakej A.

Jabatan Pengaliran dan Saliran, Selangor

11.6 million

Feb 2010

21

Proposed HDPE Submarine Pipe Crossing at Batang Paloh,Mukah Division,Sarawak (Design & Build)

PPES WORKS (Sarawak) Sdn Bhd

12.5 million

April 2011

22

Proposed 500KV Transmission Line Diversion From Existing U1,U2,U3 Janamanjung Construction of Sand Bund Access AP1,AP1/1 & AP2

Trenergy Sdn Bhd

3.05 million

December 2011

23

Projek Membina dan Menyiapkan Bekalan Air Luar Bandar (BALB) sambungan Bekalan Air Pusa ke Beladin,Bahagian Betong,Sarawak

Puncak Niaga Holding Berhad

12.1 million

June 2012

24

Dredging Work Underneath 3000 tons Shiplift at Basin Area for Messrs Boustead Naval Shipyard Sdn Bhd,Pengkalan TLDM,Lumut Perak

Macro Jaya Marine Engineering Sdn Bhd

662,000.00

October 2013

25

Dredging Works for Cooling Water Outfall Tanjung Bin,Cooling Water Intake & Outfall Project,Tanjung Bin, Johor

Murray & Roberts Marine Malaysia - Leighton Contractor (Malaysia) Joint Venture

13 million

December 2013

26

Proposed Construction of Twin 1100mm ND Raw Water Submarine Pumping Main Main Crossing Rivers (7 Nos) for Sibu Water Board

PPES Works (Sarawak)Sdn Bhd

79 million

On-Going

WIBAWA WORKS SDN BHD
37-5 Block H, Jalan PJU 1/37, Dataran Prima, Petaling Jaya          Selangor, Malaysia
Phone : +603 7804 8066
Fax: 
       +603 7804 8193
Email:      
wibawaworks at wibawa.com.my