PROJECT DATA SHEET - RM 14

PROJECT NAME:

PROPOSED 2 X 700MW COAL FIRED POWER PLANT PROJECT
SUBCONTRACT WORKS FOR SHORE PROTECTION WORKS
CLIENT :

TAISEI CORPORATION taisei logo

LOCATION:

JIMAH , NEGERI SEMBILAN , MALAYSIA

Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player

SERVICE PROVIDED:

CONSTRUCTION


CONTRACT VALUE:

RM 6 MILLION


START DATE:

FEB 2006


COMPLETION DATE:

JUNE 2007 

PROJECT DESCRIPTION:
The works comprises of ARMOUR ROCK revertment works incorporating geotextile to be constructed
for all seaward slopes of the coastal reclamation areas of 3.5km perimeter for
the 2 x 700MW Coal Fired Power Plant,Jimah,Negeri Sembilan, Malaysia.
The major works in this project carried out by Wibawa Works are:

- Revertment Profile Preparation
- Placement of Geotextile
- Rock Filter Material Installation
- Rock Armour Installation (100kg to 1 tonne)


OTHER SIMILIAR PROJECTS:

rock_revermentrock_revertment

.
WIBAWA WORKS SDN BHD
37-5 Block H, Jalan PJU 1/37,
Dataran Prima, Petaling Jaya
Selangor, Malaysia
Phone :   +603 7804 8066
Fax :       +603 7804 8193
Email:      enquiry@wibawa.com.my

   
 
Copyright WIBAWA WORKS SDN BHD . Powered by xolutions dot biz